A permit for concrete, asphalt or any other type plant established for mixing materials for paving or building may be granted for a temporary period of time of six (6) months plus one six (6) month extension. If operations exceed 12 months, a SUP application and approval will be required. Each permit shall be publicly advertised in local paper for fifteen (15) days.
Prior to ANY Temporary Batch Plant (TBP) set-up and start-up in the City of Grand Prairie the following conditions MUST be met at a minimum, in accordance with Ordinance No. 10378-2017, Article 4 of the UDC, and Article 22 of the UDC.
Any TBP that will knowingly operate more than twelve (12) months or prior to the six (6) month extension request, or need additional time to maintain operations, must file a SUP with the Planning Department prior to the extension.